A disaster recovery test starts by defining what restored service means. Identify a representative transaction, the dependencies needed to complete it and who declares recovery. Agree when measurement starts and what service level is sufficient to reopen.

Define RTO and RPO

The RTO is the target time for restoring the agreed function. The RPO sets how far back in time the last recovered data may be relative to the outage. Agree both with the service owner, accounting for impact, dependencies and alternative capacity. Record maximum tolerable downtime separately.

Test the recovery chain

In an authorised environment, recover identity, data and application in the required order. Verify emergency credentials, key availability, data consistency and reconciliation of queued transactions. Record the first successful end-to-end transaction and the timestamp of the last consistent data.

Hypothetical example and fix

A business application has a three-hour RTO and a 30-minute RPO. The first complete transaction succeeds after three hours and ten minutes. Recovered data is consistent up to 20 minutes before the outage. The test meets the RPO and exceeds the RTO by ten minutes. The team traces the delay to identity recovery, assigns an owner and schedules a second test.

Sources